Proof / Projects We Delivered
// Section 05 · Proof

Projects
we've delivered.

Recent work, the price model that delivered it, and what one of our clients said about working with us. Real engagements across RNG, water, multi-site IT, and manufacturing — all under one contract on phases 1–3. From the Boardroom to the Control Room.

// 05.01 · Recent work

Recent builds.

Each engagement follows the same Engineering → Construction → Commissioning → Operate model. Integrated Contract (from Engineering to Startup) on phases 1–3. No change orders on recent builds.

PROJECT001
SECTORRENEWABLE NATURAL GAS
LOCATIONMIDWEST · US
STATUS◆ OPERATIONAL

Renewable Natural Gas (RNG) Plants.

Engaged to review Engineer drawings, Commission Plant, Program Logic, Hand-over operations, and ongoing support to operation team.

  • PLC programming · Rockwell ControlLogix
  • VTScada deployment · 18 screens
  • UL 508A panels · 4 MCCs
  • Commissioning & operator training
24 weeks · Engineering through SAT Fixed fee · 0 change orders
PROJECT002
SECTORWATER & WASTEWATER
LOCATIONSOUTHWEST · US
STATUS◆ OPERATIONAL

Redesign and implement updated logic for Plant PLC and HMI with reporting rollout.

  • Ignition Edge IIoT · 4 sites
  • Corporate historian & data warehouse
  • Power BI executive dashboards
  • Compliance automation · state & EPA
16 weeks · Discovery through go-live Fixed fee
PROJECT003
SECTORMULTI-SITE IT
LOCATIONAZ, NM, TX
STATUS◆ ONGOING

vCAIO and vCIO + managed IT across three facilities.

  • M365 · Entra · Intune rollout
  • SD-WAN across 3 sites
  • 24/7 support · incident response
  • Quarterly strategy & roadmap
Year 3 · Monthly retainer vCIO engagement
PROJECT004
SECTORBIOGAS
LOCATIONPACIFIC NW · US
STATUS◆ COMMISSIONING

BioGas Plant control retrofit of Plant PLC and HMI.

And design / implement reporting based on compliance specifications.

  • Legacy PLC migration · Siemens S7
  • HMI redesign · 12 operator screens
  • Safety PLC integration
  • Cutover in 3-day scheduled outage
32 weeks · FEL through SAT Fixed fee · outage-critical
// 05.02 · How we price

One fixed fee.
Four phases. Zero surprises.

Most integrators quote low, then invoice change orders until the budget doubles. We quote the full scope — engineering, construction, commissioning — at a single price. We scope the project with detail, which includes commissioning startup — so we know the total work on-hand.

Typical integrator

Base bid change orders

Engineering
$100
Construction
$100
+$35 CO
Commissioning
$100
+$55 CO
Post-startup
$100
+$72 CO
Total $462 +62% over bid
// Victory

Fixed fee, end to end.

Engineering
$120
Construction
$120
Commissioning
$120
Post-startup
T&Moptional support
Total $360 22% under the overrun. Period.

Illustrative comparison. Actual savings vary. Our fixed price reflects a more thorough FEL and discovery upfront — not cheaper engineering.